top of page

The project is from 15th street down to 610 north loop   

EAST SIDE OF THE INTERSECTION ON 19TH WILL BE SHUT DOWN MONDAY JULY 1ST TO COMPLETE ASHALT TRANSITION .

            

Paving- 27th -610 North , paving bike lane and sidewalk from 25th north 

Silva Cell- working on west side of shepherd from 24th -25th street 

 

Sidewalk/Bike Lane/Driveways/Curb- working on east side of shepherd between 20th-21st, working west side from 

25th-26th 

 

Lane Closures/Sidewalk Closures:

On Shepherd:

- There will be single and double lane closures from 15th to 22nd street 

- There will be work on sidewalk to install water line. Some areas will be closed 

- There will be a single lane closure maybe in place as utilities or subcontractors are at work 

On Durham: 

- There will be single and double lane closures from 15th to 26th street 

- There will be work on sidewalk to install water line. Some areas will be closed 

- There will be a single lane closure maybe in place as utilities or subcontractors are at work 

- There will be work on sidewalk to install waterline. Some areas of the sidewalk will be closed. 

On 20th Street:

-The construction going on at the corner of 20th street and Beall is a contractor that is not in correlation with this project however any  complaints can be submitted here 

Project construction zone is from 15th street down to 610 north loop  including side streets; 15th ,16th 17th 18th ,19th ,20th ,and 24th street .

Overview.png
bottom of page