top of page

The project is from 15th street down to 610 north loop   

​

            

Paving- Shepherd east side from 24th -610 â€‹

​​

storm work being placed from 26th&27th  shepherd east 

​​

Roadway excavation from 27th -610 north 

​​

​

Sidewalk/Bike Lane/Driveways/Curb-east of Durham from 25th -26th street  

​​​

MVA doing cobble stone and patching manholes 

​

​

paving on Durham middle lane - will be open for the weekend ​

paving intersection of 25th and Durham  

 â€‹

intersection of 26th street from shepherd to Durham will be closed

anlong with 27th street going from shepherd to Durham 

​

​

​

​

​

​​

Lane Closures/Sidewalk Closures:

On Shepherd:

- There will be single and double lane closures from 15th to 22nd street 

- There will be work on sidewalk to install water line. Some areas will be closed 

- There will be a single lane closure maybe in place as utilities or subcontractors are at work 

​

On Durham: 

- There will be single and double lane closures from 15th to 26th street 

- There will be work on sidewalk to install water line. Some areas will be closed 

- There will be a single lane closure maybe in place as utilities or subcontractors are at work 

- There will be work on sidewalk to install waterline. Some areas of the sidewalk will be closed. 

On 20th Street:

-The construction going on at the corner of 20th street and Beall is a contractor that is not in correlation with this project however any  complaints can be submitted here 

Project construction zone is from 15th street down to 610 north loop  including side streets; 15th ,16th 17th 18th ,19th ,20th ,and 24th street .

Overview.png
bottom of page