The project is from 15th street down to 610 north loop   : work of the week is posted in the home page.

            

Paving :Complete paving of intersections of 26th and 27th on Durham. When  completed begin the middle lane on Durham between 24th and 26th. 

Driveways/Sidewalk/Bike Lane-Completing gaps on Shepherd East side between 17th and 19th. 

Silva Cells- Complete silva cells on the East side of Durham between 20th and 24th. 

Trees- All trees in place on Shepherd and Durham including side streets up to 20th. 

Brick Pavers- Completing all gaps. 

Lane Closures/Sidewalk Closures:

On Shepherd:

- There will be single and double lane closures from 15th to 22nd street 

- There will be work on sidewalk to install water line. Some areas will be closed 

- There will be a single lane closure maybe in place as utilities or subcontractors are at work 

On Durham: 

- There will be single and double lane closures from 15th to 26th street 

- There will be work on sidewalk to install water line. Some areas will be closed 

- There will be a single lane closure maybe in place as utilities or subcontractors are at work 

- There will be work on sidewalk to install waterline. Some areas of the sidewalk will be closed. 

On 20th Street:

-The construction going on at the corner of 20th street and Beall is a contractor that is not in correlation with this project however any  complaints can be submitted here 

Project construction zone is from 15th street down to 610 north loop  including side streets; 15th ,16th 17th 18th ,19th ,20th ,and 24th street .