top of page

First Part of The project 15th street to 20th street  : work of the week is posted in the home page.

.  We will have officers on site during day construction to assist with traffic.

              wet connections at Durham at 24th on Tuesday 12/05/23 from 8:00 PM to 5:00 AM

The intersection of 21st street and Durham Dr will be shut down vehicles will not be permitted to go east to west 

Paving- Shepherd and Durham 

 

Underground- Complete West side intersection of Shepherd at 23rd 
and 24th.  waterline on Durham going North from 25th to 610. 

 

Silva Cells- Complete 20th.  Begin placement of silva cells on the East side of 
Shepherd going North from 20th to 24th. 

 

Sidewalk/Bike Lane- Continue sidewalk on 18th.  Complete gaps on the West side 
of Shepherd between 15th and 17th (also make ready for brick pavers).   

Lane Closures/Sidewalk Closures:

On Shepherd:

- There will be single and double lane closures from 15th to 22nd street 

- There will be work on sidewalk to install water line. Some areas will be closed 

- There will be a single lane closure maybe in place as utilities or subcontractors are at work 

​

On Durham: 

- There will be single and double lane closures from 15th to 26th street 

- There will be work on sidewalk to install water line. Some areas will be closed 

- There will be a single lane closure maybe in place as utilities or subcontractors are at work 

- There will be work on sidewalk to install waterline. Some areas of the sidewalk will be closed. 

On 20th Street:

-The construction going on at the corner of 20th street and Beall is a contractor that is not in correlation with this project however any  complaints can be submitted here 

Project construction zone is from 15th street down to 610 north loop  including side streets; 15th ,16th 17th 18th ,19th ,20th ,and 24th street .

Overview.png
bottom of page