top of page

The project is from 15th street down to 610 north loop   

            

Paving- Begin step 3 on Shepherd at 24th going South. Pour S/E 
corner of Shepherd at 20th.  Pour intersections of Durham at 24th and 
27th. Waiting for final decision on storm sewer to pour Durham at 
26th. 

 

Underground Utilities- Complete storm sewer on Shepherd at 20th 
S/E corner.  Waiting for results of chlorination of waterline at 
Shepherd at 23rd and 24th and 24” waterline on Shepherd at 27th. 
Once passed we will schedule wet connections. 

 

Silva Cell- On the East side of Durham between 25th and 26th. 

 

Sidewalk/Bike Lane/Driveways/Curb- Working on 20th between 
Shepherd and Durham. Completing gaps on Shepherd between 18th 
and 20th. 

 

Lane Closures/Sidewalk Closures:

On Shepherd:

- There will be single and double lane closures from 15th to 22nd street 

- There will be work on sidewalk to install water line. Some areas will be closed 

- There will be a single lane closure maybe in place as utilities or subcontractors are at work 

On Durham: 

- There will be single and double lane closures from 15th to 26th street 

- There will be work on sidewalk to install water line. Some areas will be closed 

- There will be a single lane closure maybe in place as utilities or subcontractors are at work 

- There will be work on sidewalk to install waterline. Some areas of the sidewalk will be closed. 

On 20th Street:

-The construction going on at the corner of 20th street and Beall is a contractor that is not in correlation with this project however any  complaints can be submitted here 

Project construction zone is from 15th street down to 610 north loop  including side streets; 15th ,16th 17th 18th ,19th ,20th ,and 24th street .

Overview.png
bottom of page